Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
At the Environment, Development and Infrastructure Committee held on 3 March 2022 a programme of roads reconstruction works was endorsed.Ìý Since the programme was set, there have been significant international occurrences which have affected the prices of both fuel and bitumen.
A report providing an update on the roads reconstruction programme for 2022/23 was before the Committee for consideration.
Decision
The Committee:-
1. Endorsed the approach taken to deliver the programme within budget given the price increases; and
2. Noted that the 2022/23 footway programme would be reported to the September Environment, Development and Infrastructure Committee.
(Reference: Report by Executive Director with responsibility for Roads and Infrastructure ߣsirÊÓƵ dated 20 May 2022, submitted)
Publication date: 06/06/2022
Date of decision: 02/06/2022
Decided at meeting: 02/06/2022 - Environment, Development and Infrastructure Committee