Planning Public Access Unavailable
Planning Public Access documents will be unavailable from 5pm on Monday 10th March to allow for essential maintenance. Apologies for any inconvenience caused.
Approximate timescales for processing of applications, and guidance on contacting officers and submitting applications.
Last reviewed - 6th March 2025
We are aware some users are experiencing issues after selecting ‘View associated documents’ on Public Access receiving a core.busy error. To resolve this issue please clear the cache within your internet browser, if you continue to experience issues, please contact planning.hq@argyll-bute.gov.uk.
We are also aware of intermittent issues with the speed in which documents are viewable, the issue has been raised for further investigation.
Customers are advised that statutory planning fees were increased on the 12th December 2024, following legislation being approved in the Scottish parliament.
Our Planning Fee Guidance Notes have been updated to reflect the new fees.
For further information see: :
LDP2 has now been adopted by ߣsirÊÓƵ and Bute Council. For the avoidance of doubt, the ߣsirÊÓƵ and Bute Local Development Plan 2015 and its associated Supplementary Guidance March 2016 and Supplementary Guidance 2 December 2016 are superseded and no longer form part of the development plan.
The Development Plan for ߣsirÊÓƵ and Bute (excluding the LLTNP Area) now comprises NPF4 and LDP2; applications require to be assessed taking both National and Local policy into account but affording precedence to the content of LDP2 (as the newer document) where there is any conflict between the two.
The requirements of LDP2 will require to be applied in full to all determinations undertaken moving forward, including applications that are already in the planning system but currently remain undetermined. The requirement to retrofit updated policy requirements to applications that have been prepared and submitted during an earlier policy regime will require officers to review casework which is already at an advanced stage in its assessment and may, in some cases, impact upon officers recommendation. Officers will wherever possible seek to ensure that customers are advised of any additional impact upon determination time periods, and/or requirement for additional information arising from LDP2 at the earliest opportunity.
To avoid unnecessary delay, case officers have been instructed to review the supporting information already on file and reach their own view on whether the key aspects of the Sustainability Checklist have already been met. Where they have not, then any request for the submission of additional information should be proportionate and focus on addressing gaps in the Checklist requirements where possible. Where Agents are in a position to voluntarily complete and submit a Sustainability Checklist (for applications that remain undetermined at 5th March 2024) then this would be of assistance to officers and would be expected to expedite their ability to reach a formal determination.
Where a Sustainability Checklist has not been submitted with a new application, then officers will formally request the submission of this further information by means of a Reg. 24 request indicating that the planning authority does not intend to determine the application in the absence of the further information requested. Agents are accordingly requested to avoid unnecessary delays to determination of applications by including the completed Sustainability Checklist with all new applications submitted at this time.
Templates of both the Sustainability Checklist (reference LDP2 Policy 04 & TN06) and Sustainable Buildings Checklist are attached.
Where possible email and telephone enquiries will be responded to within 5 working days. Where this is not possible enquiries will be acknowledged and an alternative timescale for response provided.
The Central Validation Team are currently reviewing new applications within 5 working days from receipt.
All submitted applications continue to be validated in line with the National Validation Standards published by the Heads of Planning Scotland. Customers are advised to ensure that any plans and supporting documents are prepared in compliance with these requirements in order to increase the likelihood of their application being validated at the first attempt and to avoid further delays being incurred through the requirement to submit further/amended information before the application can be formally registered.
There continues to be a significant backlog of planning applications and casework arising from significant pressure upon the service from high customer demand and reduced availability of staff resource over an extended period of time. Consequently, it is currently taking longer than usual to determine ‘local’ planning applications. Whilst officers are working hard to address this issue, customers are advised that ‘local’ applications (excluding legacy items) are currently taking 14.3 weeks to determine on average. Householder applications (excluding legacy items) are currently taking 10.9 weeks to determine on average. We apologise for the delay.
Where an extension of time is required then officers will make contact to advise that determination will be delayed and advise of the revised timeline for determination of the application.
Where officers identify that there is a procedural barrier (e.g. requirement for submission of further supporting information) to reaching a positive determination of a planning application then they will seek to identify and communicate such matters at the earliest opportunity. Where it appears that there is good prospect of these issues being resolved within a reasonable timescale then officers will arrange for a formal extension to the statutory determination period.
Where circumstances allow, applications that will make a significant contribution toward the delivery of new housing or employment will be prioritised, this will also be the case where it is identified by the applicant/agent that an application is time sensitive in relation to grant funding or is urgently required for the purpose of health and/or safety.
The handling of non-statutory pre-application enquiries continues to be impacted by other work pressures, including prioritisation of planning application casework. The target period for responding to pre-application enquiries is currently 30 working days.
It is advised that pre-application responses are consequently taking longer than usual and customers are advised 59.1% of enquiries are responded to within 6 weeks.
Council offices have limited opening hours to members of the public (Service Points | ߣsirÊÓƵ and Bute Council (argyll-bute.gov.uk) As a service we are well equipped to work flexibly from home and officers are currently working on a hybrid basis. However, this does mean that officer availability in office locations is limited, and processes which require hard copy documentation may take slightly longer to complete.
You can help us by getting in touch through appropriate channels:
It is requested that applicants / agents submitting documents/applications do so either via the or electronically to the appropriate area office detailed below:
Development Management Service Plan and Customer Charter - Development Management Service Plan and Customer Charter | ߣsirÊÓƵ and Bute Council
Enforcement Charter - Planning and Enforcement Charter August 2024