ߣsirÊÓƵ

Glen Lean - bridge and road repairs

Following the partial bridge collapse and landslip on 7th October, a new temporary bridge has been installed.

29th November - The bridge arrived on site on 28 November and we carried out the additional works required, such as completing approach ramps and surfacing works.

Image
Glen Lean Bridge - new bridge being installed

We remained on track to safely re-open the route on Friday 1 December subject to no additional issues.

Image
The new Balliemore Bridge being lowered into place

This is a map which shows the new alignment of the road at Balliemore Bridge, where the new temporary bridge will go slightly upstream of the existing bridge. The old bridge will be demolished and a permanent replacement progressed for April 2024.

Image
Glen Lean Bridge - new alignment of road at Balliemore Bridge

This image shows works ongoing on the new road connections to the new bridge, upstream of the original bridge -

Image
Works for the new road connection at Glen Lean

This image shows the temporary diversion road being constructed through field to north west of the Balliemore Bridge - 

Image
Temporary diversion road being constructed at Glen Lean
Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.